Decision Maker: Executive Board
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Board considered a report from the Executive Director – Environment and Regeneration, which provided an update on progress relating to Halton’s Freeport.
RESOLVED: That
1) approval is given to allow officers to continue with due diligence with a
view to preparing a formal offer to purchase the Port of Weston using Freeport
Seed Funding;
2) Officers provide update reports to Members, as appropriate, as the
project progresses;
3) Officers work with the Combined Authority and the Freeport Board, to seek
approval from the Ministry of Housing, Communities and Local Government (MHCLG)
to reallocate remaining Freeport Seed Funds for the planning and construction
of an access road onto Port of Weston and to purchase the Port of Weston and
fund remediation works, contingency and negotiate above the initial purchase
offer; and
4) delegated authority is given to the Executive Director Environment and
Regeneration and the Director Legal and Democratic Services, in consultation
with the Deputy Leader, to draw up a collaborative agreement with prospective stakeholders as outlined in
section 3.12 of the report.
Report author: Jennifer Smith
Publication date: 17/09/2024
Date of decision: 12/09/2024
Decided at meeting: 12/09/2024 - Executive Board
Accompanying Documents: