Executive Board considered the attached report:-
RECOMMENDED: That
1) the
award of £1.675m grant funding for the Daresbury
Enterprise Zone/East Runcorn Housing Access Improvement Scheme under the DfT’s Local Pinch Point Programme be noted;
2) Council
be recommended to approve the inclusion of the LPPP scheme into the Council’s
Capital Programme at a total estimated cost of £2.394m to be phased over
2013/14 and 2014/15; and
3) in accordance with Procurement Standing Order 1.8.4, Procurement Standing Order 4.1 (Competition Requirements) be waived, and design and scheme preparation services be procured from Mott MacDonald Ltd for reasons of urgency as set out in the report.
Minutes:
Executive Board had considered a report of the Strategic Director, Policy and Resources, which advised Members of the award of grant funding through the Department for Transport’ s Local Pinch Point Programme.
RESOLVED: That Council
1)
note the
award of £1.675M grant funding for the Daresbury
Enterprise Zone / East Runcorn Housing Access Improvement Scheme under the DfT’s Local Pinch Point Programme;
2)
approve the inclusion of the LPPP scheme into the Council’s
Capital Programme at a total estimated cost of £2.394M to be phased over
2013/14 and 2014/15; and
3) note that, in accordance with Procurement Standing Order (PSO) 1.8.4, PSO 4.1 (Competition Requirements) be waived and design and scheme preparation services be procured from Mott MacDonald Ltd. for reasons of urgency, as set out in the report.
Minutes:
The Board considered a report of the Strategic Director, Policy and
Resources, which advised Members of the award of grant funding through the
Department for Transport’s (DfT) Local Pinch Point
Programme (LPPP).
The Board was advised that the LPPP
was aimed at removing bottlenecks on local highway networks and improving
access to development sites to support growth and create additional jobs and
housing. In February 2013, the Council submitted a bid for funding from the DfT from a total fund of £170m. Halton’s
bid, which was successfully fast tracked, comprised a package of schemes
designed to increase traffic capacity at three existing junctions on the A533 Daresbury Expressway. This would increase traffic capacity
at key highway access points to the Daresbury
(SciTech) Enterprise Zone and east Runcorn strategic housing development sites.
The report provided information on the
funding contribution, subject to the Council agreeing to a number of
conditions. The basis of the bid was that all works would be undertaken within
the existing Highway boundaries and delivered by March 2015.
It was noted that the Council’s
framework consultants, Mott MacDonald Ltd, had worked closely on the
preparation of the LPPP bid. However, their Engineering Consultancy Framework
Contract expired in April 2013, prior to confirmation of the DfT’s scheme approval. Members were advised that it was
proposed to waive Procurement Standing Order 4.1 (Competition Requirements) for
reasons of urgency and for this scheme only, to enable the preparatory surveys,
scheme design and project management services to proceed for this LPPP scheme
with Mott MacDonald Ltd.
RESOLVED: That
1) the
award of £1.675m grant funding for the Daresbury
Enterprise Zone/East Runcorn Housing Access Improvement Scheme under the DfT’s Local Pinch Point Programme be noted;
2) Council
be recommended to approve the inclusion of the LPPP scheme into the Council’s
Capital Programme at a total estimated cost of £2.394m to be phased over
2013/14 and 2014/15; and
3) in accordance with Procurement Standing Order 1.8.4, Procurement Standing Order 4.1 (Competition Requirements) be waived, and design and scheme preparation services be procured from Mott MacDonald Ltd for reasons of urgency as set out in the report.