114 Mersey Gateway Bridge Project - Progress Update PDF 435 KB
Minutes:
The Board considered a report of the Strategic Director, Community and
Resources, which provided a progress update on the Mersey Gateway Bridge
Project (the Project) and on the Mersey Gateway Crossings Board Limited (MGCB),
for June to December 2015.
The Board was advised that the MGCB was a special purpose vehicle,
established by Halton Borough Council, with delegated authority to deliver the
Mersey Gateway Bridge project, and to administer and oversee the construction,
maintenance and tolling of the new tolled crossings, which included the tolling
of the Silver Jubilee Bridge.
The MGCB were commissioned to deliver the Project on behalf of the
Council and operate as a commercial, not for profit organisation, on an arm’s
length basis.
The report provided an update on progress of the Project and the
performance of the MGCB in monitoring the Project, as required under the
Governance Agreement. It covered:-
· Key
Construction Events;
· Construction
of the Main Crossing, Landside and Highways;
· Most
recent activities on site;
· Programmed
activities for January 2016;
· Health
and Safety;
· Key
Performance Indicators;
· Current
Progress on the actions/risks at Financial Close; and
· Production
of an Annual Business Plan.
RESOLVED: That
1) progress with
the Mersey Gateway Bridge Project, as
set out in the report, be noted; and
2) the performance
of the Mersey Gateway Crossings Board Limited in monitoring the Project
Company’s performance, as set out in the report, be noted.