5 Schools Capital Update – 2018/19 - KEY DECISION PDF 221 KB
Additional documents:
Minutes:
The Board considered a report of the Strategic Director, People, which
provided an update on Schools Capital Funding.
The report set out details of funding received via the Healthy Pupil
Capital Fund (HPCF); additional capital works requirements for the remodelling
of Ashley School and Simms Cross School; and Social, Emotional and Mental
Health Resource Bases at Beechwood Primary School and
at Halton Lodge Primary School.
It was reported that the HPCF funding for 2018/19 was a result of
revenue generated from the Soft Drinks Industry Levy, with Halton’s
allocation being £70,362. The funding – allocated for one year only - was to be
used for improving the physical and mental health of children and young people.
It was reported that the funding would be distributed equally to Halton’s Community and Voluntary Controlled Nursery,
Primary and Special Schools.
The additional capital work requirements at
Ashley and Simms Cross Schools would allow for internal remodelling for an
enhanced learning/school environment at each school. An element of the capital works had been
approved by the Board at its meeting on 18 January 2018.
Special Provision Capital Funding had been announced by the Department
for Education for local authorities to invest in provision for children and
young people with Special Educational Needs and Disabilities. It was noted that
Halton’s allocation over a three year period would be
£500,000. It was recommended that two specific resource bases be accommodated
at Beechwood Primary School and Halton Lodge Primary
School, with additional accommodation to be built specifically to support
children in Foundation and Key Stage 1.
Reason(s) for
Decision
To deliver and
implement the capital programmes.
Alternative
Options Considered and Rejected
Not applicable.
Implementation
Date
The works at Simms
Cross School and Ashley School needed to be completed by September 2018. It was
anticipated that the works at Beechwood and Halton
Lodge Primary Schools would be completed in time for the 2019/20 academic year.
RESOLVED: That
1) the
Healthy Pupil Capital Fund (HPCF) and application procedure for 2018/19 be
noted;
2) the
proposals for capital works at Ashley School and Simms Cross Primary School,
funded from the Basic Need Capital Funding, be approved; and
3) the
proposals regarding the provision of Social, Emotional and Mental Health
Resource Bases at Beechwood Primary School and Halton
Lodge Primary School, together with the publishing of statutory notices, be
approved.