The Board considered a report of the Strategic Director, Enterprise,
Community and Resources, regarding the implementation of a regeneration
programme for Astmoor Industrial Estate.
It was reported that in March 2017, the Board approved the Mersey Gateway
Regeneration Plan Plus (the Plan), which had helped to prioritise resources
for physical and economic regeneration of eight Regeneration Impact Areas. The
Plan set out a cohesive package of development opportunities and identified key
infrastructure and enabling projects needed to support the Borough’s economic
growth. Astmoor Industrial Estate was one of the
eight Areas and an Annual Delivery Plan had been developed to steer the development
and regeneration programme for the area. This was attached to the report at
Appendix A.
The report provided the Board with a detailed summary of the Strategic
Context, the Vision and Objectives, the Masterplan and Delivery Strategy, the Funding
Profile and the Governance and Management Structure.
RESOLVED: That
1) Members
approve the two stages of public consultation to be undertaken, which will
inform a future Masterplan and Delivery Strategy for Astmoor,
as outlined in Section 3.10 of the report;
2) the
proposed approach to a regeneration programme for Astmoor,
as set out in the Annual Delivery Plan (attached to the report at Appendix A),
be noted;
3) Members
acknowledge the potential benefits from investing in Council resources to deliver a five year
regeneration programme for Astmoor, as outline in
Section 3.17 of the report; and
4) following
feedback from the consultation process, a further report be presented to
Executive Board, to seek formal adoption of a Masterplan and Delivery Strategy
for Astmoor.