Internal Audit Progress Report
Additional documents:
Minutes:
The Board received a report from the Divisional Manager – Audit, Procurement and Operational Finance, updating them on the internal audit activity since the last progress report to the Board on 23 March 2022. It also highlighted any matters that were relevant to the Board’s responsibilities as the Council’s Audit Committee.
Members were referred to appendix one, which listed all the planned work for the year and the anticipated dates that each audit would be reported to the Board. It was noted that the planning and completion of work was subject to change, but this represented the best estimates at the current time.
Further to the approval of the Audit Plan on 23 March 2022, Members were advised that good progress had been made against the Plan so far, with most outstanding work relating to the 2021/22 Audit Plan now complete or nearing completion. The remaining work from 2021/22 would be reported to the next meeting of the Board.
Appended to the report were the executive summaries of the reports issued numbering 2 to 16, as listed in paragraph 4.2.
The Board discussed the difficulties the Council was experiencing recruiting staff and it was noted that a report would be submitted to the next Corporate Policy and Performance Board exploring these issues.
RESOLVED: That the Internal Audit Progress Report and comments made be noted.