Venue: Marketing Suite, Municipal Building. View directions
Contact: Caroline Halpin on 0151 471 7394
No. | Item |
---|---|
MINUTES Minutes: The Minutes of the meeting held on 2 April 2009 were taken as read and signed as correct record. |
|
(NB: Councillor Nelson
declared a personal interest in the following item due to being a Chair of
Governors at the Grange Schools.) (Councillor Harris
declared a personal interest in the following item due to being a Governor at The |
|
Approval of BSF Outline Business Case - KEY DECISION PDF 36 KB Additional documents: Minutes: The Board considered a report of the Strategic Director, Children and Young People which detailed the Outline Business Case (OBC) and sought approval for the submission of the OBC to the DCSF by 22 April 2009. It was reported that Halton submitted its Strategy for Change Part 1 in July 2008, which had now been agreed. The Strategy for Change Part 2 was submitted on 19 November 2008. It was noted that conditional approval was granted on the basis that additional information was provided by 27 February 2009 and the Authority was given permission to develop its OBCase. It was reported that notification had now been received which confirmed that the outstanding requirements from Strategy for Change Part 2 had now been met. The Board was advised that the OBC consisted of the following key sections plus associated appendices:
Explanations of each section were set out in the report for Members’ consideration. It was reported that the current Funding Allocation Model adjusted for Private Finance Initiative (PFI) credits was £175 million. Members were advised that this figure would cover the costs of Halton’s BSF Programme. It was noted that the estimated costs to deliver ICT solution for the BSF Programme was £23.5 million and included a 0.5 million contingency. The available funding was a combination of the BSF funding and a contribution of £200 per secondary pupil per annum, which would be secured for each secondary pupil. It was reported that for the OBC cases the authority must also confirm that sufficient resources were available to meet the procurement and BSF team costs. It was noted that the total resources available would meet the £4 million requirement for the Authority. In addition the Board was informed that revenue affordability of the Programme must be confirmed at OBC and in the Halton BSF Programme the building programme was being supported produced in two ways; through PFI where there was more than 70% new build and through the conventional funding solution for Design and Build. Detailed in the report was a table that set out all the additional contributions which would be made to the BSF Programme. It was noted that the one off (single) contributions had been used to reduce the ongoing annual costs of the PFI schools. In addition, the funding to reduce the annual affordability gap had been identified. The Board considered the affordability section and noted the four key issues as follows; · is the capital expenditure affordable? · are revenue consequences affordable? · are the costs of the team affordable? and · are the costs of IT affordable? Members were advised all the key issues above were affordable based on the model outlined in the report. Arising from discussion Members requested that a breakdown of costs and plans of each site be circulated and presented in the near future. REASON FOR DECISION The Outline Business Case must be completed as part of ... view the full minutes text for item 146. |
|
(NB: Councillor Nelson
declared a personal interest in the following item due to being a Chair of
Governors at the Grange Schools.) (Councillor Harris
declared a personal interest in the following item due to being a Governor at The (Councillor Swain
declared a personal interest in the following item due to beig
a Governor at |
|
BSF Secondary Re-organisation - KEY DECISION PDF 52 KB Additional documents:
Minutes: The Board received a report of the Strategic Director, Children and
Young People which summarised the response to the statutory consultation undertaken on secondary Special Educational Needs (SEN)
unit provision in Halton. An outline of
the decision making process was also included for Members’ consideration. A further update on the outcome of the
statutory consultation was circulated at the meeting following the end of the
representation period on 2nd April 2009. Members were also advised of the school organisation proposals required
in Runcorn for The Heath Specialist Technology College, The Grange
Comprehensive, The Grange Junior, The Grange Infant, The Grange Nursery and It was reported that the proposals recommended the discontinuance of the
7 place EBD Unit at Halton High ( Detailed in the report were the proposals to establish the secondary SEN
resources provision as follows: The Grange
Comprehensive (Community School) – The school would provide resource provision for 11 pupils with a
diagnosis of Autistic Spectrum Disorder (ASD), 5 of these places would be
reserved for outreach support for pupils in other high schools within the
borough. In addition, there would be
resource provision for 10 pupils with speech and language and communication
needs. Saints Peter and
Paul Catholic College (Voluntary Aided Catholic) - The school would provide
resource provision for 11 pupils with a diagnosis of Autistic Spectrum Disorder
(ASD), 5 of these places would be reserved for outreach support for pupils in
other high schools within the borough. The Bankfield ( Wade Deacon High ( REASONS FOR DECISION The proposals for secondary and secondary special provision must be agreed prior to the submission of the Outline Business Case. ALTERNATIVE OPTIONS
CONSIDERED AND REJECTED Alternative options have been considered and assessed during the
consultation process. IMPLEMENTATION DATE The proposals for
SEN unit provision must be agreed by 9th April 2009 and will be
implemented by September 2011. The proposal to
commence the consultation on Runcorn secondary provision must be agreed by 9th
April 2009, however, the increase in numbers at The Heath Specialist Technology
College are not scheduled to be implemented until the school has been rebuilt
as part of the BSF Programme (2012/2013).
The proposals for the re-organisation of The Grange Comprehensive,
Junior, Infant and Nursery are scheduled to be implemented in April 2010. The date for the establishment of the Academy
to replace Halton High is September 2010. RESOLVED: That 1) Approval be given to commence the informal
consultation process to expand the |
|
Decision on BSF Funding and Procurement - KEY DECISION PDF 30 KB Minutes: The Board considered a report of the Strategic Director, Children and Young People which set out the range of Procurement Standard Documents and Standard Form Agreements, that were required to be submitted on 22 April 2009 as part of the BSF Programme. The Board was advised of the range of Procurement Standard Documents as follows:
It was reported that templates were available for the documents above
which needed personalising in line with each Programme requirements. The documents must then be agreed with
Partnerships for schools. It was further advised that there was a suite of Standard Form
Agreements which must be approved by Partnerships for Schools, detailed as
follows:
REASON FOR DECISION The procurement Standard
Documents and Standard Form Agreements must be agreed and submitted with the
Outline Business Case on 22 April 2009. ALTERNATIVE OPTIONS CONSIDERED AND REJECTED Not applicable. IMPLEMENTATION DATE The Outline
Business Case and supporting documents must be submitted to the DCSF and PfS by 22 April 2009. RESOLVED: That 1) the Chief Executive be authorised to agree
the supporting Procurement Standard documents and Standard Form Agreements
prior to the submission of the business case to Partnerships for Schools and
DCSF; and 1) the procurement process to be applied to the
BSF Programme is that which is set out in the Partnerships for School guidance. |
|
Procurement of a Joint Local Education Partnership with Warrington Council - KEY DECISION PDF 33 KB Additional documents: Minutes: - The Board received a report of the Strategic Director, Children and Young People which outlined the proposals and gain approval to establish a joint Local Education Partnership (LEP) with Warrington Borough Council. It was reported that a LEP was a public private partnership between the LA, BSF for the Future Investments LLP (BSFI) and a private sector partner selected in open competition under the European procurement rules. The LEP was therefore a joint venture company whose primary purpose was to ensure that BSF investment was efficiently and effectively used to deliver transformation. The key aims of the LEP were outlined in the report for Members consideration. The Board was advised of the proposal of a joint LEP be procured between Halton and Warrington Borough Council. It was noted that this would allow both Councils to have a joint BSF team that would manage the business cases and procurement preparation. It was further noted that this would strengthen both BSF teams and allow for revenue savings from both Councils. Members were informed that approval in principle was being considered by Warrington Council in April with formal consideration in May 2009. It was further reported that approval by both Councils would be subject to the agreement of a Memorandum of Understanding (MoU) which would outline the operational and revenue implications, role of external commissioned services, the scope of the LEP and the governance arrangements for the Board. Appended to the report was a summary of the style, type and provision of the MoU. It was noted that a full copy of the MoU could be made available on request. REASON FOR DECISION A decision is required on the position in terms of the Joint LEP prior to the submission of Outline Business Case on 22 April 2009. ALTERNATIVE OPTIONS CONSIDERED AND REJECTED Not applicable. IMPLEMENTATION DATE The Outline Business Case must be submitted to the DCSF and PfS by 22 April 2009. RESOLVED: That 1) Approval be given to enter into collaborative arrangements with Warrington Borough Council for the purposes of procuring a Private Sector Partner to participate and invest in a Local Education Partnership (LEP); 2) The arrangements in 2.1 of the report be subject of an agreed and signed Memorandum of Understanding (MoU) between both Councils; 3) The scope of services to be obtained through joint procurement and the governance arrangements to be set out in the MoU; and 4) The Chief Executive, in consultation with the Leader and the Executive Board Member for Children and Young People, be authorised to approve the final MoU and take whatever actions necessary to give effect to this decision
|
|
(NB: Councillor Harris
declared a personal interest in the following item due to being a Governor at
All Saints Upton CE Primary School.) |
|
Children's Centre Phase 3 Capital - KEY DECISION PDF 40 KB Minutes: The Board considered a report of the Strategic Director, Children and Young People which identified the availability of Phase 3 capital funding for children’s centres and proposed deployment of this resource to maximise access to children’s centre services. It was reported that since April 2006, local authorities have had strategic responsibility for delivering children’s centres, to reflect the mainstreaming of children’s centres as a universal, national programme. Children’s centre services were planned and delivered in partnership with the NHS, Jobcentre Plus and a wide range of voluntary, private and community organisations based on local need. Members
were advised that children’s centres were not currently recognised in
legislation, although the integrated services which they offered to children
and families had a statutory basis in the local authority duties under the
Childcare Act 2006 to provide integrated early childhood services. However, it
was noted that the Government’s current proposals contained within The
Apprenticeships, Skills, Children and Learning Bill, to establish children’s
centres as a recognised part of children’s services infrastructure that had direct bearing on the future
developments of the centres. It was
further advised that the proposed legislation would mean that in future,
whether or not an establishment was described as a children’s centre would be a
matter of law. It was reported that the
Government proposed to use the Act to establish that all children’s centres in
existence at the date of the Royal Assent were captured as children’s centres
for the purpose of the statutory requirements. It was
reported that Local Authorities, working with their statutory partners, would
be required to assess the need for children’s centres in their area, and to
establish and maintain sufficient children’s centres to meet that need. The
purpose of the proposed legislation was to provide children’s centres with a
statutory footing, so that their provision was not seen as the outcome of
time-limited funding regime, but became a long term statutory commitment and
part of the established landscape of early years
provision. The
Board was advised that the intention was to reflect in the legislation and
associated statutory guidance practice in localities which was outlined in the
report for information. It was
further noted that under phase 1 and 2 of the programme, twelve children’s
centres had been established in Halton.
Each children’s centre was intended to serve a
“reach” of between 800 and 1200 children under 5 years within the locality. All
twelve centres had been formally designated as children’s centres by
Government. The
Board was informed that Government required Phase 3 children’s centres
(2008-11) to be situated outside the most disadvantaged areas and would
therefore offer a less intensive level of support than those phase 1 and 2
centres serving families in the 30% most disadvantaged areas. It was
reported that Phase 3 was supported by capital funding of £521,866. It was proposed that this funding is used to
enhance the facilities at existing children’s centres which were outlined in
the report for Members consideration. REASON FOR DECISION The Local ... view the full minutes text for item 150. |