Capital Programme 2013-14 - KEY DECISION PDF 30 KB Additional documents: Minutes: The Board considered a report of the Strategic Director, Children and
Enterprise, which provided an update on the Schools Capital Programme for
2013/14. The Board was advised that the schools capital grant allocations were
normally announced by the Department for Education in December each year.
However, the capital allocations of Basic Need, Condition Maintenance and
Devolved Formula Capital would be confirmed by the end of January 2013. It was reported that an important part of the capital programme was the
Capital maintenance Programme, where key elements of school buildings were
replaced in a rolling programme of works which could only be carried out during
school holidays to minimise disruption. The Board was advised that design work which would allow scoping and
procurement as necessary, would be carried out in advance so that works could
commence on site during the Easter and Summer school holidays. Details of these
works were attached at Appendix 1. A further report would be submitted to the Board once the capital
allocations had been announced. Reason(s) for
Decision To
deliver and implement the capital programme. Alternative
Options Considered and Rejected Not applicable. Implementation
Date 1 April 2013. RESOLVED: That 1) the
position in respect of the announcement of the capital funding for 2013/14 be
noted; 2) the
proposals to be carried out from Capital Maintenance be agreed; and 3) a
further report be submitted to Executive Board when capital allocations are
confirmed. |
|||
Re-designation and extension of age range at Ashley School - key decision PDF 42 KB Additional documents:
Minutes: The Board considered a report of the Strategic Director, Children and
Enterprise, which provided a summary of the outcome of the first phase of
consultation on the re-designation and extension of the age range at Ashley
School. Details of the outcome from the
consultation exercise, which took place in December 2012, were attached at
Appendix A. The key issues raised during the process were noted as: · the size of provision
– would it be large enough; · training for staff; · expansion of the
physical environment of the school; · increased choice; · whether the school
would have to change its status to an
Academy; · extension of the age
range from 16 – 19; and · impact on the provision
currently offered by Riverside College. It was reported that the re-designation and expansion of the age range
at Ashley School provided the Local Authority with the opportunity to address a
gap in provision and ensured that children and young people of Halton had
access to appropriate provision within their community. The next stage of statutory consultation, which it was reported would
now commence on 30 January 2013, would seek views on the following: · Re-designation of
Ashley School so that it can cater for
vulnerable pupils, with a diagnosis of Autism and for those with
identified Social Communication Needs who have a moderate to high learning
ability; · Provision of 70
places for pupils aged 11-16; and · Extension of the age
range to 19 with the provision of up to a maximum of 42 post-16 places Reason(s) for
Decision A gap in provision had been identified for
vulnerable pupils with a diagnosis of Autism and for those with identified
Social Communication Needs who had a moderate to high learning ability. Alternative Options
Considered and Rejected No change to the
current provision was considered.
However this was rejected as it would not address the gap in provision
identified and the views of the majority of the consultees. Implementation
Date The next phase of the consultation was
scheduled to commence on 31st January 2013 for 6 weeks. RESOLVED: That the Board 1)
notes
the response to the first phase of consultation; 2)
agrees
the revised post-16 capacity; and 3)
approves the statutory consultation. |
|||
Community Safety Portfolio |
|||
The Cheshire Police and Crime Plan - Making Cheshire an even safer place to live PDF 42 KB Minutes: The Board considered a report of the Strategic Director, Communities, on the draft Cheshire Police and Crime Plan for 2013/16. The Board was advised that, under the Police Reform and Social Responsibility Act 2011, the Police and Crime Commissioner must produce a Police and Crime Plan (the Plan) for their area for their term of office. The development of the Plan took into account arrange of information regarding local and national priorities through stakeholder analysis. It was noted that there were five key objectives with a number of performance measures designed to monitor progress. These five objectives, detailed in the report were:- · Enhance front line Policing to enable the Constabulary to prevent and further drive down crime; · Protect Cheshire’s communities from harm; · Support victims and witnesses of crime and take a robust stance in tackling those who continue to re-offend; · Continue to build on the strong partnership between the Police and the communities of Cheshire; and · Ensure the delivery of an efficient and effective Police service. This would include building on the use of innovative technology to deliver better services to the communities of Cheshire. Members were advised that the Plan had been considered at the recent meetings of the Safer Policy and Performance Board and the Safer Halton Partnership and those comments had been included in the formal Halton Borough Council consultation response. In addition, Cheshire Fire and Rescue Service had advised that they would respond direct. RESOLVED: That the response to the plan as set out in Section 6.0 of the report be approved. |
|||
Resources Portfolio |
|||
Discretionary Non Domestic Rate Relief PDF 26 KB Minutes: The Board considered a report of the Strategic Director, Policy and
Resources, on the renewal of discretionary non-domestic rate relief. The Board was reminded that, at its meeting on 13 December 2012, it had
approved the granting of discretionary rate relief for all existing recipients,
except for Halton Community Transport and Moorfield
Sports and Social Club, for whom additional information was requested. This
additional information now confirmed that the two latter organisations were
both still eligible to receive the discretionary rate relief. Appendix 1
contained a summary of the financial implications. It was noted that discretionary rate relief was usually granted to
organisations for a three year period, with Regulations requiring twelve
months’ notice of ceasing that relief. Such notice had been given to these
organisations in March 2012. RESOLVED: That, under
the provisions of Section 47, Local Government Finance Act 1988, discretionary rate
relief be granted to the following organisations at the percentage indicated,
for the period from 1st April 2013 to 31st March 2016:
|
|||
(N.B. The following Councillors declared a Disclosable Other Interest in the following item of
business for the reasons stated: Councillor R Hignett
as a member of the Joint Venture Board; Councillor D Cargill
as a member of the Merseyside Phasing-in Sub Committee – Euro Structural
Funding; Councillor Polhill as a
Member of the Enterprise Zone Board) |
|||
Daresbury Funding - KEY DECISION PDF 31 KB Minutes: The Board considered a report of the Strategic Director, Children and Enterprise which updated them on the funding for the development of the Sci-Tech Daresbury. It was reported that the key strategic site and international hub for world class science at Sci-Tech Daresbury became an Enterprise Zone in August 2011. A Daresbury Joint Venture Partnership, set up in 2010, had been successful in securing £9.77m of Regional Growth Funding (RGF) grant-aid. The grant application had four key components, detailed in the report as Project Tech Space, Power (Phase 1), Environmental Improvements and Transport Improvements. The Board was advised that the bid included a realistic target on job creation and that the total cost of the works was estimated to be £22m. Details of funding secured were given in the report and the Board noted that a further bid for the Growing Places Fund (GPF) had been approved in November 2012, and an offer letter awaited. A condition of the GPF funding was that it be re-invested in the Liverpool City Region, with the first repayment due in August 2015 and the final one in December 2019. Reason(s) for Decision On 17 October 2012, the Daresbury JV Partnership was informed that it had been successful in securing £9.77m of Regional Growth Fund funding and £1.8m of Growing Places Funding. Alternative Options Considered and Rejected If the offer of these funds was not accepted, the Borough would lose the opportunities provided by £11.57m plus match funding. Implementation Date The final grant offer will be signed off by 19 April 2013 following due diligence. RESOLVED: That the Board 1) accepts the offer of £9.77m of Regional Growth Fund (RGF) from the Office for Business, Innovation and Skills (BIS); 2) accepts the offer of £1.8m of Growing Places Funding (GPF) from the Liverpool City Region Local Enterprise Partnership; 3) gives authority for the Council to enter into back-to-back contracts with Joint Venture Partners for the delivery of the project; and 4) agrees
to the Council entering into a claw back agreement with Joint Venture Partners
at Daresbury, in accordance with the RGF and GPF
offers. |
|||
Neighbourhood Leisure and Sport Portfolio |
|||
Halton Housing Strategy 2013-2018 - Draft - KEY DECISION PDF 41 KB Additional documents:
Minutes: The Board considered a report of the Strategic Director, Communities on a draft of Halton’s Housing Strategy 2013-18, for public consultation. The Board was advised that the Local Government Act 2003 required local authorities to produce a housing strategy, to give an overview of housing in their district and to set out priorities for action. The strategic housing role was defined in the document Homes For the Future (2007) as providing “leadership, planning and delivery”. It was noted that there had been significant achievements since the last Housing Strategy was published in 2008, and these were detailed in the report. The Draft Housing Strategy 2013-18 had taken a slightly different approach from previous years, in that two documents had been produced. These were attached to the report, the first being a short easy to read document which focused on the strategic objectives, priorities and planned activities for the next three years (Appendix A) and a supported evidence paper setting out the context in which the Strategy had been developed (Appendix B). The Draft Strategy contained three overarching strategic objectives with priorities within each, as set out in the report. It will be the subject of a seven week consultation period with partners, stakeholders and residents. Reason(s) for Decision Under Part 7 of the Local Government Act 2003, local authorities were expected to produce a Housing Strategy, which gave an overview of housing in their district and set out priorities for action. Alternative Options Considered and Rejected Not applicable. Implementation Date May 2013. RESOLVED: That the content of the Draft Housing Strategy be approved and the arrangements for public consultation, as outlined in paragraph 3.4.1 of the report, be noted. |
|||
MINUTES ISSUED: 25 January