Minutes:
The Board considered a report of the Strategic Director, Policy and Resources, on the construction of the western access road to the 3MG HBC Field development and a waiver of Procurement Standing Orders.
The report provided details of the previous approval of the preliminary design of the access road, the preliminary estimates and tender submissions, and the business case for the waiver of Procurement Standing Orders.
Reason for Decision
Continuing progress on the provision of infrastructure to
support the 3MG HBC Field development would enable the draw-down of Regional
Growth Fund and Growing Places Fund allocated to the 3MG Programme that had
been identified for this purpose. Construction
of the western access road removed elements of risk to programme delivery,
enhanced the value of the site and its attractiveness to potential developers /
customers and took advantage of the competitive tender submission for the
construction of the road from Balfour Beatty Civil Engineering Ltd (BBCEL).
Alternative Options Considered and Rejected
The contract for the
construction of the western access road could be re-tendered. However, this would incur additional
procurement costs, including tenderer pre-qualification and selection,
preparation of tender documentation, management of the tender process and
tender evaluation and award. The process
was estimated to add approximately £75,000 to the cost of the scheme and would
take around 20 weeks from inviting expressions of interest to award of
Contract. The existing tender from BBCEL
was considered to offer excellent value for money and there was no guarantee
that a new tender process would result in lower prices.
The original plan
was for the transport infrastructure relating to the development of HBC Field
to be delivered through a Development Agreement with Pro Logis
UK (PUK), the Council’s development partner.
For the reasons stated in paragraph 3.1.4 of the report to the Executive
Board, PUK were not in a position to let a contract for the road construction. Therefore if the Council accepted and wished
to continue to make progress as set out in Paragraph 9.0 of the report, it was
not an option to wait for a pre-let agreement to be signed with a customer.
The scope of works
tendered in July by PUK included the whole of the western access road and
bridge (as designed by Atkins) from Newstead Road
into the proposed HBC Fields development site.
This was on the basis of a potential customers’
requirements. The contract could be
retendered on this same scope of works, however, the
value of the scheme would be above the public procurement thresholds and would
require re-tendering with the consequent additional costs and delays as set out
in paragraph 10.1.
In addition to the reasons for rejection described in paragraph 10.3, the scope of the scheme for the construction of the western access road had been modified from that originally tendered by PUK, because at this stage we did not know whether the site would eventually be developed for single or multiple occupiers. This retained a degree of flexibility in the future layout of the road south of the railway lane.
Implementation Date
Subject to Board approval, the advance site investigations and further
design work would commence in early June 2012. It was anticipated that contract
award would follow confirmation of amended design approvals in July 2012.
RESOLVED: That
1)
the Board approves the project as described in the Preliminary estimates
section of the report;
2) the Operational Director Policy, Planning and Transportation
be authorised to award the contract for
the construction of the 3MG Access Road to the Contractor Balfour Beatty Civil
Engineering Ltd. in the sum of £4,330,784;
and that in the light of the exceptional circumstances, namely that:
(i) Compliance with Standing Orders would result in a clear
financial detriment to the Council; and
(ii)
Compliance with Standing Orders would result in the Council having to forego a
clear financial benefit; and
(iii)
Compliance with Standing Orders would result in the Council having to forego a
clear commercial benefit;
and in accordance with Procurement
Standing Order 1.8.3, Procurement Standing Orders 2.2 – 2.12 and 2.14 be waived
on this occasion.
3) the Operational Director Policy, Planning
and Transportation be authorised to award a contract for advance site
investigation works (comprising sampling and testing) to the contractor Balfour
Beatty Civil Engineering Ltd. in the estimated sum of £15,000 and that in the light of the exceptional
circumstances, namely that:
(i) Compliance with Standing
Orders is not practicable because the Council’s requirements can only be
delivered by a particular supplier;
and in accordance with Procurement
Standing Order 1.8.3(e), Procurement Standing Order 4.1 be waived on this
occasion.
4) the Operational Director Policy, Planning
and Transportation be authorised to award the contract for further scheme
design work to Atkins (Engineering and Design Consultants) in the estimated sum
of £95,000 and that in the light of the
exceptional circumstances, namely that:
(i) Compliance with Standing Orders is not practicable
because the Council’s requirements can only be delivered by a particular
supplier;
and in accordance with Procurement
Standing Order 1.8.3(e), Procurement Standing Order 4.1 be waived on this
occasion.
5)
the Chief Executive, in consultation with the Leader and the following
Portfolio holders; Physical Environment, Transportation and Resources, be
authorised to take such action as he
judges necessary to implement the construction access road to 3MG.
Supporting documents: